City and Town Notification for Roadway Work

MassDOT will be conducting work in your community in the near future.  The following project information is being forwarded to you for distribution to affect City/Town Departments.

 

Project Location (City/Town):   Abington-Brockton North Quincy @ Boundary Ave. and Chestnut St.

Estimated Start Date of Work:  5/6/21 for detour

Project Type:  Intersection Improvements and Related work (installation of a roundabout)

Resident Engineer and Contact Information: Christopher Sera: 617-308-8604 christopher.sera@dot.state.ma.us

Description of Work:  Installation of T-100 mountable curbing, pouring and curing of stamped concrete truck mountable apron.  Detour of North Quincy St. and Chestnut St. required to perform work.

Contractor and Contact Information:  R.M. Pacella:  Noel Farah project manager 508-809-4100.  Justin Schultz superintendent 978-857-0021

Hours of Operation (Day/Night):  7am-3pm for most activities.  Potential for longer days as needed.  Detour in effect 24 hours/day from May 6th to May 10th to allow for curbing installation and pouring/ curing of concrete.

Description of Traffic Management:  Police details, message boards, detour signage, complete roadway detour. 

Estimated Duration of Work:  Duration of detour is expected to be May 6th 8am to May 10th 8am. 

Additional Information:  North Quincy St. NB will be detoured left onto Boundary St., right on to South Franklin St. NB (Rte. 37).  Traffic wanting to use Chestnut St. (from Boundary Ave.) will then be directed up to Plymouth St./Abington Ave (Rte. 139) to Chestnut St. .  Local traffic will be allowed to homes around the project.